New Office IT Setup Checklist Template

The desks arrive on schedule. The fibre circuit is still waiting for the landlord to sign a form, and the room set aside for the network turns out to be a cupboard with no cooling.

This free new office IT setup checklist is for IT managers, MSPs and the IT lead on an office project, whether the site is a first office, a new branch or a move. It covers the building survey, internet circuits and other long-lead orders, the comms room and structured cabling, the network, Wi-Fi, phones and meeting rooms, testing and a go-live approval. When servers or comms equipment are coming from another site, a relocation path appears for the shutdown, the move and the power-on. The output is a working office before staff arrive and an as-built pack you can trust.

Use This Template Free See Live Example
No Credit Card Required

Last reviewed: October 2026

The Move Plan Owns the Date. This Checklist Owns the Infrastructure.

An office project runs two plans side by side. Facilities owns the lease, fit-out, furniture and staff announcements. IT owns everything that must be live before the first person sits down: the circuit, the cabling, the comms room, the Wi-Fi and the phones. Most day-one failures happen where one side assumed the other had it covered.

This page is the IT plan. It starts as soon as the address is likely, because the circuit order is the longest lead time on the project, and ends with the network handed to operations. Moving existing servers is a conditional phase here rather than a separate checklist, since the comms room, the cabling and the power-on depend on each other.

Facilities-led move

Lease, fit-out, people

Owner: operations or the office manager.

Covers: the lease exit, furniture, staff communications and address updates.

Template: Office Relocation Checklist.

New office IT setup

This checklist

Owner: the IT lead or the MSP.

Covers: circuits, cabling, comms room, network, Wi-Fi, phones and building systems, tested and approved before move-in.

Optional: moving servers and comms kit from another site.

Network upgrade

New kit in an existing site

Owner: the network team.

Covers: swapping switches, firewalls or circuits inside a maintenance window, with a rollback.

Template: Network Upgrade & Cutover Checklist.

What the New Office IT Setup Checklist Covers

Seven phases run from the first building survey to the handover. It is run once per office opening or move. Two answers on the first task decide whether the building-systems task and the relocation phase appear, and a named approver signs off go-live before staff move in.

Phase 1

Phase 1: Survey & Requirements

The first task records whether servers or comms equipment are moving from another site, and whether building systems will use the IT network. Those answers show or hide later tasks.

  • Open the project and record the site, move-in date and scope answers — peak-day headcount, whether existing servers or comms kit are moving here, who leads any relocation and who approves go-live
  • Survey the building with the landlord’s plans and the fit-out drawings — riser routes, ceiling voids, floor boxes, the room set aside for comms and where the provider’s line enters
  • Count the endpoints room by room — data outlets, access points, printers, meeting room screens, phones, cameras and door readers, each marked on the floor plan
  • Ask the landlord what the lease allows — drilling, cable routes through shared risers, roof access, out-of-hours working and who signs the provider’s access forms
  • Agree with the business what must work on day one — internet speed and resilience, guest Wi-Fi, and which systems can wait a week
Phase 2

Phase 2: Circuits & Long-Lead Orders

  • Order the primary internet circuit as soon as the address is certain — dedicated fibre is quoted in weeks or months, and longer when the provider has to dig
  • Order a second connection on a different path — another provider or technology, so one damaged cable in the street does not close the office
  • Return the landlord access forms the provider sends — in the UK this is usually a wayleave, and an unsigned one quietly moves the install date
  • Order network kit and the uninterruptible power supply (UPS) — switches, firewall and access points too, worked back from the date the comms room must be ready
  • Arrange a temporary connection if the circuit will be late — a mobile data router or business broadband line, sized for the first weeks
Phase 3

Phase 3: Comms Room & Structured Cabling

  • Specify the comms room’s power, cooling and security — dedicated circuits, cooling sized to the heat load, a lock, and no water pipes overhead
  • Size the UPS to the load and the runtime you need — enough to ride through a short outage or shut equipment down cleanly, with spare capacity for growth
  • Issue the cabling specification to the installer — Category 6A to the TIA-568 standards, two cables to each access point position, the labelling scheme and the test reports you expect
  • Install racks, patch panels and cable management — with space left for the provider’s equipment and a few years of growth
  • Collect a certification test result for every link — each outlet labelled to match the patch panel and the floor plan
  • Inspect the room before any equipment goes in — temperature, power, earthing, labelling, the lock fitted and construction dust cleared
Phase 4

Phase 4: Network, Wi-Fi & Rooms

The building-systems task appears only when the first task says access control, CCTV or other building systems will use the IT network.

  • Design the IP plan and VLANs — staff, voice, printers, guest, building systems and management, each with its own range
  • Configure and install the firewall and switches from your standard — configuration backed up before anyone relies on it
  • Produce a predictive Wi-Fi design, then update it after the fit-out — glass partitions, lift shafts, kitchens and filing walls all change coverage
  • Mount the access points and walk a validation survey — record signal and interference in every area against the design target
  • Connect printers, meeting room screens and video equipment — on the right VLAN, with a test call from every room
  • Set up phones and test emergency calling from the new address — in the US, Kari’s Law and RAY BAUM’S Act require direct 911 dialling and a dispatchable location
  • Put access control, CCTV and building systems on their own segment — with the PoE budget checked and the installers’ remote access agreed in writing
Phase 5

Phase 5: Server & Comms Equipment Relocation

These tasks appear only when existing servers or comms equipment are moving from another site, and go to the relocation lead named on the first task.

  • List every device that is moving and decide what is not — kit near the end of its support may cost less to replace than to move and insure
  • Write the shutdown and power-on order — storage and hosts first on the way up, then directory and DNS, then applications; the reverse on the way down
  • Take full backups and prove a restore before shutdown — and keep one copy that does not travel on the same vehicle as the servers
  • Photograph and label every cable, port and rack position — so the rack at the new site is rebuilt exactly as it stood
  • Book specialist IT movers with transit insurance that covers the real value — confirm anti-static packing, the insured sum and who travels with the kit
  • Rack, cable and power on in the agreed order at the new site — check each layer is healthy before starting the next
  • Have each service owner confirm their system works — logins, data, scheduled jobs and integrations, recorded before staff rely on them
Phase 6

Phase 6: Testing & Go-Live Approval

The go-live approver named on the first task records a decision, and the checklist halts until they do.

  • Test from every floor and room before staff arrive — internet, Wi-Fi roaming, printing, phones and the systems the business named as day one
  • Fail over to the second connection and back — time both directions and confirm calls and VPNs recover
  • Cut mains power to the UPS in a quiet hour — confirm the alerts arrive and equipment holds or shuts down as designed
  • Approve go-live — the approver records Approved or Not approved with the test results attached; staff do not move in until they do
  • Put someone from IT on the floor for the first morning — the edge cases arrive with the people, not with the testing
Phase 7

Phase 7: Handover & Records

  • Hand over the as-built pack — floor plan with outlet numbers, rack elevations, the IP plan, cable test reports and circuit references
  • Add the site’s devices to monitoring, backup and the asset register — with locations, serial numbers and owners
  • Record warranty, support and circuit contract dates — so renewals and minimum terms are known before they bite
  • Send the old site’s remaining equipment to decommissioning — servers through their own checklist, everything else through asset disposal
  • Review the project 30 days after opening — tickets raised, Wi-Fi complaints and what to change in this template next time

Comms Room and Cabling Defaults Worth Writing Down

Most new-office problems were decided in the specification, months before move-in. These are starting points for the documents Phases 3 and 4 hand to installers. Where a standard sets the figure it is named; the rest is common practice to tune.

Item Sensible default Where it comes from
Copper cable runsNo more than 90 m of fixed cable, 100 m including patch cordsTIA-568 permanent link and channel limits
Cable categoryCategory 6A for new installationsCommon practice; carries multi-gigabit to access points with headroom
Access point positionsTwo Category 6A cables to each oneTIA-568.1-E-1 (2023)
Cable acceptanceA certification report for every permanent linkInstaller handover; keep it in the as-built pack
Comms room temperature18–27 °C at the equipment air intakeASHRAE TC 9.9 recommended envelope
UPS runtimeLong enough to ride through short outages or shut down cleanlyA judgement; size to the load plus growth
Wi-Fi coverage for callsAbout −67 dBm or stronger in every working areaA widely used design target for voice over Wi-Fi
Internet resilienceTwo connections on physically separate routesCommon practice for any site that cannot close

Two items cause most late surprises. The first is the circuit. Business fibre usually needs a provider survey, and often a signed landlord access agreement before engineers can run cable through shared areas. UK government guidance describes wayleaves as the most common form of that agreement. Ask the landlord who signs them on the day you order.

The second is moving existing servers. If Phase 5 appears, treat the move as a planned outage with a rollback point: the backup proven before shutdown is the way back if a disk does not survive the journey. A server with a year of support left can cost more to pack, insure and rebuild than to replace with a cloud service or new kit built through the Server Setup & Provisioning Checklist.

Why Run Office IT Setups in CheckFlow?

1

The relocation path only when there is kit to move

Conditional logic reads the first task. A greenfield office sees no relocation tasks at all. A move with a rack of servers gets the full shutdown, transport and power-on sequence, assigned to the relocation lead picked in a members field.

2

Long lead times treated as deadlines

Dynamic due dates count each task from the day the project opens, so the circuit order is due in the first week rather than whenever someone remembers. Overdue orders show on the owner’s own task list.

3

An as-built pack that builds itself

Test reports, rack photos and the IP plan attach to the tasks that produced them. The go-live approval halts the checklist until the approver decides, and the activity trail shows who tested what and when.

Run this alongside the Office Relocation Checklist, which covers the lease, fit-out, staff communications and address changes, and agree the move-in date between the two. Network changes at an office you already occupy belong in the Network Upgrade & Cutover Checklist. Servers left behind at the old site leave through the Server Decommissioning Checklist, and the IT Asset Management Checklist keeps the register in step with what moved.

Once the office is open, each new starter’s laptop and accounts follow the new hire IT setup checklist.

Frequently Asked Questions

How far ahead should IT start planning a new office?

+

As soon as the address is likely, and before the lease is signed if you can. The internet circuit sets the timetable: dedicated fibre needs a provider survey, sometimes new ducting and a landlord access agreement, and quotes run to weeks or months. Three to four months before move-in is a sensible minimum for the order.

What does a small office comms room need?

+

A lockable space with dedicated power circuits, cooling for the heat the equipment gives off, a UPS, a rack with room to grow, and no water pipes overhead. ASHRAE’s recommended range for IT equipment intake air is 18–27 °C, which a closed cupboard full of switches can exceed quickly. Add a temperature sensor that alerts someone.

How do you move servers to a new office safely?

+

Plan it as an outage with a way back. Take full backups and prove a restore before shutdown, keeping one copy apart from the servers in transit. Write the shutdown and power-on order around dependencies, photograph and label every cable, and use movers who specialise in IT equipment with insurance that covers its real value. At the new site, bring each layer up and check it before the next.

Do I need a Wi-Fi survey for a small office?

+

A predictive design from the floor plan is worth doing for almost any office, because it decides where the access point cables go before the ceilings close. After installation, a validation walk with a survey app or tool confirms coverage in every room. Glass meeting rooms, lift cores and kitchens are where prediction and reality most often differ.

What network cabling should a new office use?

+

Category 6A is the usual choice for new installations, because newer access points use multi-gigabit uplinks and cabling outlasts several generations of switches. Keep fixed runs within 90 m so the full channel stays inside 100 m, ask for two cables to every access point position, and do not accept the installation without a certification test report for each link and labels that match the floor plan.

Is CheckFlow free for this template?

+

14-day free trial, no card required. The Business plan is $10 per user per month after the trial. Full details at checkflow.io/pricing.

Open the Doors With the Network Already Working

Free trial — no credit card required.